Bodhee Prep-Online CAT Coaching | Online CAT Preparation | CAT Online Courses

Get 30% OFF on CAT Crash Course. Code: LASTLAP. Course starts from 18th Sept Enroll Now

CAT 2019 Quant Question with Solution 15

Question:
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?

Show Answer

Correct Answer: 13

Let one machine completes 1 unit of work per day.

Given, two machines can finish the job in 13 days

Therefore, the work of 2×1×13 = 26 units.

Also, let on man completes m units of work per day.

From the given condition:

3m+8×1 = 2(8m+3×1)

Or m = $\frac{2}{13}units$

Let it require ‘x’ number of men to complete the work in 13 days.

Therefore, xm×13 =26 units

Or x = 13 men


CAT Online Course
Also Check: 841+ CAT Quant Questions with Solutions

CAT 2019 Slot-1


CAT 2019 Slot-2

CAT online Courses

CAT 2023 Mock Test Series

  • 400+ Topic Tests
  • 45 Sectional tests
  • 20 Mock Tests (Video Solutions)
  • Only at INR 2499

20% Discount Code: GET20

FREE CAT Prep Whatsapp Group

CAT 2023 Online Course at affordable price