CAT 2021 Quant Question [Slot 1] with Solution 04

Question
Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is
  1. 5
  2. 8
  3. 6
  4. 7
Option: 4
Solution:
Let the total amount of work be 60 units. Then Anu, Vinu, and Manu do 4, 5, and 3 units of work per day respectively. On the 1st day, Anu and Vinu work. Work done on the 1st day = 9 units On the 2nd day, Manu and Vinu work. Work done on the 2nd day = 8 units This cycle goes on. And in 6 days, the work completed is 9+8+9+8+9+8 = 51 units. On the 7th day, again Anu and Vinu work and complete the remaining 9 units of work. Thus, the number of days taken is 7 days.
CAT Online Course @ INR 9999 only

CAT 2021 Quant questions with Solutions

CAT 2023
Classroom Course

We are starting classroom course for CAT 2023 in Gurugram from the month of December.
Please fill the form to book your seat for FREE Demo Classes

CAT 2023 Classroom Course starts in Gurgaon