Question: A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
  1. 4 days
  2. \(\frac{4}{3}\)days
  3. 3 days
  4. 12 days

Correct Option:2