Question:
Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

13.5
11
12
14.5
Show Answer
Correct Answer: 1
Let r and g be the rates of work of Ramesh and Ganesh respectively.
Let $(\mathrm{r}+\mathrm{g}) 16=1$
$\Rightarrow(r+g)=\frac{1}{16}$
$(r+g) 7=\frac{7}{16}$
Remaining work to be done $=\frac{9}{16}$
Given, $(0.7 r+g) 10=\frac{9}{16}$
$7 r+10 g=9 r+9 g$
$g=2 r$
$r=\frac{1}{48}$
$g=\frac{1}{24}$
Time taken by g alone to complete the work $=\frac{\frac{9}{16}}{\frac{1}{24}}$=13.5

Get one day FREE Trial of CAT online Full course FREE Registration
Also Check: 841+ CAT Quant Questions with Solutions


CAT Quant Online Course


  • 1000+ Practice Problems
  • Detailed Theory of Every Topics
  • Online Live Sessions for Doubt Clearing
  • All Problems with Video Solutions
₹ 2999

CAT 2018 Questions Paper with Solution PDF Download


CAT 2018 Quant Questions with Solutions

CAT 2018 Slot-1


CAT 2018 Slot-2


Back to Main Page


CAT 2018 Quant Questions
4.9 (97%) 20 vote[s]