Question:
When they work alone, B needs 25% more time to ?nish a job than A does. They two ?nish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and ?nally B works alone to complete the remaining 5% of the job. In how many days can B alone ?nish the entire job?

20
16
22
18
Show Answer
Get one day FREE Trial of CAT online Full course FREE Registration
Correct Answer: 1

Let us assume that A can complete 'a' units of work in a day and B can complete 'b' units of work in a day. 

A works alone till half the work is completed. 

A and B work together for 4 days and B works alone to complete the last 5% of the work. 

=> A and B in 4 days can complete 45% of the work.

Let us assume the total amount of work to be done to be 100 units.

4a + 4b = 45 ---------(1)

B needs 25% more time than A to finish a job. 

=> 1.25*b = a ----------(2)

Substituting (2) in (1), we get, 

5b+4b = 45

9b = 45

b = 5 units/day

B alone can finish the job in 100/5 = 20 days. 

Also Check: 841+ CAT Quant Questions with Solutions


CAT Quant Online Course


  • 1000+ Practice Problems
  • Detailed Theory of Every Topics
  • Online Live Sessions for Doubt Clearing
  • All Problems with Video Solutions
₹ 2999

CAT 2018 Questions Paper with Solution PDF Download


Back to Main Page


CAT 2018 Quant Questions
5 (100%) 10 votes